Omexom will renovate HV line and build substations in Hægebostad

The client is Agder Energi Nett AS.

Omexom Norway, department Distribution Network South / East, has been commissioned to completely renew the high-voltage line between Bjærum and Hellås in Hægebostad. The client is Agder Energi Nett AS.

Today’s line is from the 1950s and will be replaced with a new 22kV line – distributed on just under 2 km as the crow flies and just under one kilometer by cable.

At Krossen and Hellås, substations will also be set up, in addition, Omexom will dismantle old masts and lines in an environmentally sound manner. If old material and insulators are discovered in the terrain, this must be cleaned up and.